Project Overview
Emergency switchgear repairs and replacement following arc flash damage.
The scope of this project was to repair all damage associated with Arc Flash, which occurred in the Main Electrical Gear on 11.16.21, located inside Building 40 at the Kansas City, VA Medical Center. Onsite replaced 2 damaged Switchgear Cubicles. Schneider Electric was commissioned to test the equipment prior to returning it to service. Onsite was awarded this emergency project based on our quick response time and working relationship through our JOC contract with the KC VA Medical Center. Long lead times on parts after Covid delayed getting the gear back in service.